Technical data

108
Confidential
Start up sequence
Step 1: DC Switch turn on
Step 2: AC connecting
Inverter behavior:
Case 1: DC voltage between 100V (200V) and VStart up; Input power> ca. 8W
-> Inverter starts up display: waiting for Sun
-> Green LED „Power“ flashes
Case 2: DC voltage > Start up voltage (200V/360V default)
-> Inverter starts checking of grid parameters (Voltage, Frequency) and measures
the Insulation resistance Riso. Green LED flashes
-> Inverter performs the internal self-test
-> This process takes about 30 ... 60 seconds.
The measured values are displayed on the screen. The green LED flashes.
-> If are all parameters in order the inverter connects to the power and feeds Energy to the grid.
The green LED is lit. Accumulated energy and other values are displayed
After startup:
Set time and date!
Countries setting check
In case of more inverters monitoring, set individual address for each one inverter.