Technical data

Table Of Contents
COMpact 3000 analog/ISDN/VoIP - Firmware Version 4.0 - Version of the Manual 03 02/11 71
Installing and Switching on the PBX
Commissioning
Turning on the PBX
Commissioning
The commissioning of the PBX includes switching on the PBX, as well as connecting the PC
for configuration. If the VoIP and ISDN end devices are connected, they also have to be
commissioned.
Turning on the PBX
Requirements:
The power plug included in the package
For connecting to the power plug (step 1): cover panel is removed
1. Insert the barrel connector of the power plug into the barrel socket of the PBX.
The figure in the following shows the position of the barrel socket under the cover
panel, as well as the connection set up to the power plug.
2. Replace the cover panel.
3. Insert the power plug into a freely accessible 230 V Schuko socket
The "Power" LED shines several seconds in red and orange, as specified below. If the
LEDs shines green, the PBX is ready for operation.
“Power” LED: Status of the PBX:
Shines red The boot partition is being tested.
Shines orange The hardware data and the kernel are being loaded from
the partition.
Blinks orange The kernel drivers are being loaded.
Shines orange The PBX application is started.
Shines green The PBX is ready for operation.