Technical data
Manual VIPA System 300S SPEED7 Chapter 1 Basics
HB140E - CP - RE_343-1EX71 - Rev. 09/46 1-7
Hints for the project engineering
For the project engineering of a SPEED7 system please follow this
approach:
• Project engineering of the SPEED7-CPU and the internal DP master (if
existing) as CPU 318-2DP (318-2AJ00-0AB00)
• Project engineering of the real plugged modules at the standard bus
• Project engineering of the internal Ethernet PG/OP channel after the
real plugged modules as virtual CP 343-1 (Setting of IP address, subnet
mask and gateway for online project engineering)
• Project engineering of an internal CP343 (if existing) as 2. CP 343-1
• Project engineering and connection of the SPEED-Bus-CPs res. -DP
master as CP 343-1 (343-1EX11) res. CP 342-5 (342-5DA02 V5.0)
• Project engineering of all SPEED-Bus modules as single DP slaves in a
virtual DP master module (speedbus.gsd required)
Note!
Please do always use the CPU 318-2DP (6ES7 318-2AJ00-0AB0/V3.0)
from Siemens in the hardware catalog to configure a CPU 31xS from VIPA.
For the project engineering, a thorough knowledge of the SIMATIC
manager and the hardware configurator from Siemens is required!
The hardware configurator is part of the Siemens SIMATIC manager. It
serves the project engineering. Please look at the hardware catalog for the
modules that may be configured.
For the deployment of the System 300S modules at the SPEED-Bus the
inclusion of the System 300S modules into the hardware catalog via the
GSD-file speedbus.gsd from VIPA is necessary.
Overview
Requirements