Setup guide
Resetting the Nearchive Enclosure Power Supply Modules
71
n
The rebuild process can be run in the background, but if you continue to use the system
during the rebuild, the rebuild time will be significantly extended. Also, you will not have
redundancy protection during the rebuild period.
10. The 3DM Home menu will show the rebuild progress (Rebuilding X% completed). The
3DM utility will post a message when the rebuild is complete.
Resetting the Nearchive Enclosure Power Supply
Modules
If the Nearchive enclosure does not start when you press the Power switch, the power supply
modules might have tripped to prevent them from an over-power condition.
To reset the power supply modules:
1. Turn the Power switch on the power supply modules to the off (O) position. The units
have three redundant parallel power supplies with an AC switch for each supply. Turn
off all three switches.
2. Wait 10 seconds.
3. Turn the Power switches to the on (|) position.