User`s guide

Installation and Setup
33
Introduction
Before the instrument arrived, you may have received the
pre-installation checklist given in this chapter to ensure that your lab
is setup correctly. If you did not receive the checklist, refer to the
pre-installation checklist in this section to ensure that you have
enough space for the GC and all the related support equipment and
that the electrical and gas supplies meet the requirements of the
ATD /TD .
Installation consists of the following 7 steps:
1. Unpack the ATD/TD and site it correctly up on the lab
bench.
2. Connect gas and electrical supplies to the ATD/TD.
3. Connect gas and electrical supplies to the GC.
4. If you are using the Control Software, you must
connect and configure a suitable PC.
5. Connect any optional accessories.
6. Leak test the system.
7. Perform a test run to ensure all system components are
operational.
Normally, a PerkinElmer service technician will install and
configure your instrument. Installation and setup of the ATD/TD is
relatively straightforward. The instructions provided here are for the
experienced user.
Pre-installation Checklist
Contact your safety engineer, industrial hygienist, environmental
engineer, or safety manager before you install or use this instrument
to determine if there are any other considerations in addition to the
information listed below.
Before the instrument arrives:
1. Check your laboratory environment and ensure that the
temperature and humidity settings are within the
acceptable operating range for the ATD/TD. See