Instruction manual

AC Power and Grounding
2-12
Installation, SPM, Maintenance, and Troubleshooting Supplement
WARNING:
When installing the control unit, make sure you meet the following
grounding requirements:
The control unit, the central office trunk protector, and the AC power
service panel should be as close to each other as possible.
Because equipment can be located throughout a building, the National
Electrical Code requires that the ground point for the central office
trunk protector be bonded to the AC power ground as shown in
Figure 2-3.
The AC outlet and the single-point ground bar must be properly
grounded as shown in Figure 2-1 and Figure 2-3.
Each control unit ground-screw terminal must be connected to the
single-point ground bar by a #12 AWG or a #14 AWG solid copper wire.
Figure 2-1 and Figure 2-3 show this connection.
This wire run should be as short as possible, preferably within
5 feet (152 cm), and not to exceed 10 feet (305 cm). See Approved
Grounds later in this chapter, for more information.
The AC outlet must be connected to the 145D protector with a #12
AWG or a #14 AWG solid copper wire.