User Manual
Table Of Contents
- ROMB User Manual
- Contents
- Chapter 1: Introduction
- Chapter 2: Installation
- Chapter 3: Installing Drivers
- Chapter 4: RAID Management Utility
- Chapter 5: WebPAM
- Logging into WebPAM
- Logging out of WebPAM
- Managing Users
- Viewing Host Management
- Making Utility Configuration Settings
- Managing the Controller
- Managing Physical Drives
- Managing Logical Drives
- Viewing All Logical Drives
- Creating a Logical Drive
- Creating a JBOD Disk
- Deleting a Logical Drive or JBOD Disk
- Viewing Logical Drive Information
- Making Logical Drive Settings
- Migrating a Logical Drive
- Rebuilding a Logical Drive
- Synchronizing a Logical Drive
- Viewing Logical Drive Initialization
- Activating a Logical Drive
- Responding to a Critical or Offline Logical Drive
- Managing Spare Drives
- Chapter 6: Technology
- Chapter 7: Support
- Appendix A: Partition and Format
- Appendix B: Upgrades
- Index
Software ROMB User Manual
88
4. From the Policy dropdown menu, choose:
• Fix if you want Synchronization
• Redundancy Check if you do not want to correct inconsistencies
5. Click the Enable option.
6. Click the by Day, by Week or by Month option.
7. From the dropdown menus, select a start time and a day of the Week or
Month, if applicable.
Start time is based on a 24-hour clock.
8. Click the Schedule button.
Cancelling a Schedule
To cancel a scheduled Synchronization or Redundancy Check:
1. Click the Logical Drive View icon in Tree View.
2. Click the Logical Drive icon.
3. Click the Synchronization tab in Management View.
4. Click the Disable option.