Cancelling a Schedule
To cancel the scheduled Rebuild:
1. Click the Logical Drive View icon in Tree View.
2. Click the Logical Drive icon.
3. Click the Rebuild tab in Management View.
4. Click the Disable option.
Automatically After Drive Replacement
Automatic rebuilding after you replace the failed drive is possible under the
following conditions:
The logical drive is a RAID 1, 5, or 10.
See “Creating a Logical Drive” on page 70.
The replacement drive has adequate capacity.
Automatic Rebuild Status is Enabled.
See “Making Controller Settings” on page 59.
WebPAM will report the automatic rebuild in its user interface, as well as via
popup messages, and via email, depending on your settings (see page 51).
Automatically using a Hot Spare Drive
Automatic rebuilding using a hot spare drive is possible under the following
conditions:
The logical drive is a RAID 1 or a three-drive RAID 5.
See “Creating a Logical Drive” on page 70.
You have a hot spare drive with adequate capacity.
See “Creating a Spare Drive” on page 94.
Automatic Rebuild Status is Enabled.
See “Making Controller Settings” on page 59.
WebPAM will report the automatic rebuild in its user interface, as well as via
popup messages, and via email, depending on your settings (see page 51).
You can replace the failed physical drive at your convenience.