User Manual
Table Of Contents
- ROMB User Manual
- Contents
- Chapter 1: Introduction
- Chapter 2: Installation
- Chapter 3: Installing Drivers
- Chapter 4: RAID Management Utility
- Chapter 5: WebPAM
- Logging into WebPAM
- Logging out of WebPAM
- Managing Users
- Viewing Host Management
- Making Utility Configuration Settings
- Managing the Controller
- Managing Physical Drives
- Managing Logical Drives
- Viewing All Logical Drives
- Creating a Logical Drive
- Creating a JBOD Disk
- Deleting a Logical Drive or JBOD Disk
- Viewing Logical Drive Information
- Making Logical Drive Settings
- Migrating a Logical Drive
- Rebuilding a Logical Drive
- Synchronizing a Logical Drive
- Viewing Logical Drive Initialization
- Activating a Logical Drive
- Responding to a Critical or Offline Logical Drive
- Managing Spare Drives
- Chapter 6: Technology
- Chapter 7: Support
- Appendix A: Partition and Format
- Appendix B: Upgrades
- Index
Software ROMB User Manual
84
Click the Abort button to stop the Rebuild. After an abort, click the Restart button
to start the Rebuild from the beginning (zero percent).
Scheduled
Scheduling allows you to perform the Rebuild at a time when there is less
demand on the RAID system.
To schedule a Rebuild:
1. Click the Logical Drive View icon in Tree View.
2. Click the Logical Drive icon of the logical drive you want to rebuild.
3. Click the Rebuild tab in Management View.
4. Select the physical drive you want to rebuild.
Available drives have a black frame. Selected drives have a red frame.
5. Click the Enable option.
6. From the dropdown menus, select a start time.
Start time is based on a 24-hour clock.
7. Click the Start At field to display a popup calendar.
8. Click the start date in the calendar or enter a date manually.
9. Click the Schedule button.