Unit installation
BMB01 – Installation Guide
Figure 4 Attaching the BMB01 to the DIN rail
REAR DIN
RAIL MOUNT
PIVOT DOWNWARDS AND
BACKWARDS
SPRING LOADED CLIP
8. Connect the field wiring to the connectors, as required by system design. Reconnect each connector;
see
Figure 5.
Figure 5 Connecting the field wiring
Field wiring shown as an example.
Connections will differ depending
on system design.
PROCESSOR
HEALTH LED
COMMS LED
The connectors are pluggable so the BMB01 can be replaced without having to disconnect
individual wires.
9. Secure the BMB01 unit on the DIN rail using end-stop or wiring terminals on both sides of the unit.
10. Ensure that the unit is powered on.
The PROCESSOR HEALTH LED flashes to indicate that the unit is powered on and the processor is
fault free; see
Figure 5.
11. The installation is now complete and ready for system commissioning.
When the BMB01 is correctly configured and commissioned the LEDs (see
Figure 5) flash as follows:
• PROCESSOR HEALTH LED: flashes approx once per second
• COMMS LED: flashes very fast
See Section “
3 Controls and Indicators” (page 9) for further details.
Issue: 02 Complete, Approved