Product manual
Commissioning, Introduction
Technical Product Manual - DCT1800-GAP
TD 92093 (1/LZBNB 103 108 R4D) / 2006-03-09/ Ver.C
© 2006
1
Chapter 1 Introduction
This section describes the visual inspection and tests that must be executed after completing the
installation and initialization of the DCT1800-GAP system. The purpose of the visual inspection and
tests is to verify that all installation activities have resulted in a correctly functioning DCT1800-GAP
system. If it appears that a part is malfunctioning while the system is installed correctly (i.e.: no cabling
faults, no configuration faults), the technician must consult the maintenance section included in this
manual for fault finding.
Chapter 1 : Introduction
Introduces you to the section.
Chapter 2 : Visual inspection and tests
Describes the items that can be checked visually and all the tests that must be
executed to verify that the system functions correctly.