Measure the building diagonally again to make
sure the building is square. The building should
be square at the base and at the top. This will
make roof panels fi t better and holes will better
align.
If a Roof Strengthening Kit was purchased,
assemble and install before attaching Roof
Panels.
Whenever a crimped rib and an uncrimped rib meet,
place the crimped rib UNDER the uncrimped rib.
Crimped Rib
Uncrimped Rib
Be sure to carefully follow the Roof Panel
Placement Order Diagram on this page.
8462
5209
6538
5209
8463
8463
5209
6538
5209
8462
4
10
8
6
2
3
9
7
5
1
FRONT
Roof Panel Placement Order
If Roof Beam holes do not line up with Roof
Panel holes, shift the building from left to right. If
this does not help, your building may not be level.
Shim the corners until holes line up.
Roof Install Prep Page
Use the information on this page to complete steps 13 thru 15.
The building is square when diagonal measurements are equal.
34BI