Installation Guide
Step 17
SO30 ctr
 Parts Needed For 
Ridge Caps & Panels
 6538 Roof Panel (2)
 6797 Ridge Cap (3)
6188 Right Roof Panel (1)
6189 Left Roof Panel (1)
1 Install the third ridge caps 6797 
overlapping the second ridge caps 
while installing the remaining roof 
panels 6538. Hint: The bolts on the 
ridge cap need to be left loose to 
move the ridge cap to the side and 
overlap the ribs of the next roof panel. 
Cover the notched areas of the roof 
panels with strips of weather stripping 
tape and continue weather stripping 
the ridge.
2 Install the left 6189 and right roof 
panel 6188 as you unroll the weather 
stripping tape, and press it down. 
Fasten the lower end of the panels 
to the side wall angles using screws 
and washers.
3 Fasten the roof panel ribs, peak 
caps and ridge caps together using 
bolts and nuts. 
Reducing Large Gable Bulge
Loosen eight bolts and nuts shown. Apply 
pressure with one hand at the peak of the 
gable and tighten bolt #1. Keeping pressure 
on the gable work down the slope tighten-
ing each bolt. Excess material will overlap 
smaller gable at seam. Once material bulge 
is worked out tighten four vertical bolts that 
connect the large and small gables.
Peak Cap
STEP
2
6797
STEP
2
6797
6188
STEP
3
STEP
1
Cut
Weather Stripping
and Fold Under
6189
6538
6538
6797
#1
#2
#3
#4
(72)
(36)
30