01BP 717950816 Owner’s Manual & Assembly Guide www.arrowsheds.com Model No. PM1012 10’ x 12’ Gloves must be worn at all times to reduce risk of injury! Nominal Size Customer Service: 1-800-851-1085 or assist@arrowsheds.com BUILDING DIMENSIONS Approx.† Size 10’ x 12’ 3,0 m x 3,6 m Storage Area 115 Sq. Ft. 729 Cu. Ft. 2 10,7 m 20,6 m3 * See Inside for Detailed Safety Information.
SAFETY PRECAUTIONS... 02H Safety precautions MUST be followed at all times throughout the construction of your building! Care must be taken when handling various pieces of your building since many contain sharp edges. Please wear work gloves, eye protection and long sleeves when assembling or performing any maintenance on your building. Practice caution with the tools being used in the assembly of this building. Be especially familiar with the operation of all power tools.
ASSEMBLY TIPS & TOOLS 03A Watch the Weather Closely: Be sure the day you choose to install your building is dry and calm. Do NOT attempt to assemble your building on a windy day. Be careful on wet or muddy ground. Use Teamwork: Two or more people are required to assemble your building. One person can hold the parts or panels in place while the other person fastens them together and handles the tools. This makes the process of assembling your building faster and safer.
04A FREQUENTLY ASKED QUESTIONS Q. How long will it take to assemble the building? A. Assembly time depends on a variety of factors, including roof design, tools available, DIY skill and the pace at which you work. Guidelines for each shed assembly are approximate AFTER completion of the base, and assume two or more people working on the assembly. Generally, you should plan on at least one day working with someone who can assist you; again, after constructing the base.
05A Q. What kind of base do I use? A. You can: •Use an Arrow Base Kit •Pour a concrete slab •Build a wood deck/floor (use exterior-grade plywood) •Use patio blocks •Build on crushed gravel, dirt or grass Arrow provides a base kit accessory that is an option for most building sizes. If you are building a wood deck/floor, an Arrow floor frame kit on top of your deck/floor assembles in minutes and provides a floor frame suitable for a 5/8” exterior-grade plywood floor (not included).
Q. What if the rear wall angle and channels are too large to fit inside of the rear wall panels? A. Check the dimensions of wall assemblies. They should be slightly smaller than the floor 06A frames. Lay the assemblies on top of the rear floor frame and pull them up to the top of the wall panels causing the corner panels to stand erect and not lean inward. Caution: Be careful to not scratch the panels on the way up. Q. The wide rib always overlaps the crimped rib. Is there ever an exception? A.
HARDWARE LIST... 07BP Hardware Views by Key No. 1 Key Part No. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 65103 65900A 65923 65004 6228 66183L 66183R 66769 67468 66045 66646 67545 66382 Part Description Qty. Hex Nut (#8-32) Black Screw (#10B x 1/2) (13 mm) Bolt (#8-32 x 3/8) (10 mm) Screw (#8AB x 5/16) (8 mm) Track Supprt Left Roof Trim Cap Right Roof Trim Cap Door Slide Peak Cap Handle Washer Sheet Weather Stripping Lower Door Guide 139 8 139 382 2 2 2 4 2 2 7 1 4 List 2 11/32 Hex.
PARTS LIST... Key No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Part No.
ASSEMBLY BY KEY NO.
ASSEMBLY BY KEY NO.
ASSEMBLY OVERVIEW Build the Floor Frame Install Posts, Wall Angles, and Door Jambs Install Siding Panels Attach Gables and Roof Beams Install Roof Panels, Ridge Cap, Side Trim, and Corner Cap Install Doors Shed is now complete.
CONSTRUCTING A BASE... 12BP No matter which of the options below you choose for a base, an ARROW ANCHORING KIT is recommended as an effective method of properly securing your building after assembly is complete. OPTION 1: Directly on ground (earth) Assemble your building directly on level ground (grass, dirt, rock, sand, etc.). If you choose this option Arrow has a simple kit available to provide a floor inside the shed to keep stored items off the ground.
Step 1: Floor Frames You will need for this page: (QTY: 8) Washers are to be used on painted parts only. Washers are not necessary on unpainted parts and there are not enough to use on every screw and bolt. 10392 4 Side Floor Frame 10392 BUILD TWO (2) FRAMES 1 13AW Overlap two (2) Side Floor Frames as shown and secure with four (4) bolts. Two (2) bolts must enter from bottom. Assemble a second Side Floor Frame Assembly by repeating part 1.
Step 1: Continued You will need for this page: (QTY: 5) 8936 14A 2 Rear Floor Frame 8936 Assemble the Rear Floor Frames. 3 Overlap two (2) Rear Floor Frames as shown and secure with five (5) bolts. Two (2) bolts must enter from bottom. 4 Check that the finished length of the Assembly is 119 3/8” (303,2 cm). Set aside for use in Step 5. 8936 Bolts thru Top. Bolts thru Bottom.
Step 1: Continued You will need for this page: 2 9367 Front Floor Frame (QTY: 8) 8934 1 119 3/8” 303,2 cm Finished Length Ramp Overlap Length 7 3/8” 18,7 cm 9367 5 15A Overlap the Ramp and two (2) Front Floor Frames so that four (4) holes align at each end as shown. Insert four (4) screws in each end. 8934 6 Confirm that the drain holes are facing outside the building. Check that the finished length of the Assembly is 119 3/8” (303,2 cm). Set aside for use in Step 5.
Step 2: Wall Frames You will need for this page: 5986 Rear Wall Angle (QTY: 1) 1 2 Overlap two (2) Rear Wall Angles so that five (5) holes align as shown. Insert a bolt and nut through the center hole. Check that the finished length of the Assembly is 118 1/8” ( 300,0 cm) set aside for use in Step 7. 5986 Slide parts together until five (5) holes align. 5986 5986 Place bolt thru center hole only.
Step 2: Continued You will need for this page: 10394 4 89 7/8” 228,3 cm Finished Length Side Wall Angle (QTY: 2) Overlap Length 7 5/8” 19,4 cm Overlap two (2) Side Wall Channels so that three (3) holes align as shown. Insert a bolt and nut through the center hole. Check that the finished length of the Assembly is 89 7/8” ( 228,3 cm) set aside for use in Step 10. 2 3 17BP Repeat Part 2 to build a second set. BUILD TWO (2) 10394 Slide parts together until four (4) holes align.
Step 3: Roof Beams You will need for this page: 10568 BUILD TWO (2) BEAMS Roof Beam (QTY: 16) 1 10568 4 18AW Overlap two (2) Roof Beams so that the bottom slots align as shown. Insert six (6) bolts and nuts as shown below. 2 Insert two (2) bolts and nuts into slots on bottom of the Beam as shown. Check that the finished length of the Assembly is 142 3/8” (361,6 cm). Set aside for use in Step 12. 3 Repeat parts 1 & 2 to build a second Roof Beam Assembly.
Step 3: Continued You will need for this page: 10568 4 142 3/8” 361,6 cm Finished Length (QTY: 14) 19AW Overlap Length 6 1/8” 15,6 cm Roof Beam Overlap two (2) Roof Beams so that bottom slots align but DO NOT INSERT BOLTS. Next, overlap two (2) more Roof Beams to form a second Roof Beam Assembly. DO NOT INSERT BOLTS . Place both Roof Beam Assemblies back-toback to form a Double Beam. Insert ten (10) bolts and nuts as shown below. Insert four (4) bolts and nuts into slots from bottom.
Step 4: Door Track You will need for this page: 6403 Track Splice (Painted) (QTY: 4) 1 Door Track END VIEW 4 9366 2 CORRECT Insert screws into bottom side only. The Gables will fasten to the Door Track using the holes on the top side. 1 2 Position the Door Slides in the Door Track. Check that the finished length is 118 1/8” (300,0 cm). Set aside for use in Step 7. INCORRECT Long Leg on top.
Step 5: Frame Assembly You will need for this page: (QTY: 8) (QTY: 2) 21A Assemblies from Step 1: • • • Front Floor Assembly (1) Side Floor Assembly (2) Rear Floor Assembly (1) Do NOT fasten your Floor Frames to your Base at this time. You will anchor your building after it is erected. If using a Floor Frame Kit, you must wait until after assembly to install it. 1 Assemble Floor Frame with two screws at each corner as shown.
Step 6: Posts/Top Frames You will need for this page: 9196 2 (QTY: 10) Corner 9197 2 22BP Assembly from Step 4: • Door Track Assembly (1) Corner Post The remainder of the building assembly requires many hours and more than one person. Do not continue beyond this point if you do not have enough time to complete it today. Partially assembled building can be severely damaged by light winds.
Step 6: Continued 23BP You will need for this page: Assemblies from Step 2: (QTY: 6) • • Rear Wall Angle Assembly (1) Side Wall Angle Assemblies (2) 3 Fasten the rear wall angle assembly behind the top of the rear posts using screws. 4 Fasten the side wall angle assemblies behind the top of the side posts using screws. Side wall angles overlap rear wall angle in corners.
Step 7: 24BP Splice Post/Door Jamb You will need for this page: (QTY: 8) (QTY: 10) 9195 (QTY: 2) 1 Splice Post 9198 2 Side Splice Post 9194 2 Door Jamb The door jambs reinforce the door opening and provide an attractive trim. The splice posts support the walls. 1 Position splice post at the center of the rear wall and fasten using nuts and bolts into rear wall angle and screws into rear floor frame. Hint: Measure or count holes to determine if post is centered on rear.
Step 8: Studs You will need for this page: (QTY: 10) 9199 10 25BP The studs provide a surface for attaching the siding panels. Siding Stud 1 Following dimensions, measuring from the ends of the angles, place a stud between each corner and splice post at the rear and two on sides of building. Position stud inside top angle and fasten with a screw. 2 Rest bottom tab (large hole) outside floor frame. Do not fasten tab at this time. Repeat procedure for the remaining studs aound the building.
Step 9: Side Siding 26BP You will need for this page: • • 6287 Side Siding (5 board) (4) 5335 Side Siding (3 board) (4) (QTY: 24) The floor frame must be square and level or holes will not align. 1 Slide side sliding (5 board) into channels of corner and splice posts, flat edge upward, bottom edge down resting on floor frame. Always follow this pattern. Fasten bottom edge and tab of stud to floor frame using screws. Fasten center to stud with screws. Do not fasten flat edge yet.
Step 9: Continued You will need for this page: • 5336 Side Siding (6 board) (4) (QTY: 24) 3 Install side siding (6 board) to the top as before. Remove and reuse screw in angle to fasten top siding. 4 From inside building, fasten siding to corner posts using screws. 5 Repeat steps 1 through 4 for opposite side of building.
Step 10: Rear Siding You will need for this page: Parts needed: • • • (QTY: 36) 8736 Rear Siding (5 board) (2) 5307 Rear Siding (3 board) (2) 5306 Rear Siding (6 board) (2) 1 5307 (3 board) Slide rear siding (5 board) into channel of corner and splice posts fastening to rear as shown in previous step. Install rear siding (3 and 6 board) to complete each section of rear wall. 5306 (6 board) 8736 (5 board) 2 28BP Install rear siding (3 board and 6 board) to complete each section of rear wall.
Step 11: Front Siding You will need for this page: Parts needed: (QTY: 24) 1 • • • 8737 Rear Siding (5 board) (2) 5291 Rear Siding (3 board) (2) 5290 Rear Siding (6 board) (2) Slide front siding (5 board) into channel of corner post and door jamb. This siding is fastened from the inside, using screws into post and jamb. Front Panels Fasten at Corner Posts & Door Jambs from the Inside 5291 8737 FRONT 5290 2 Install front siding (3 board) and front siding (6board) to complete both front sections.
BP Step 12: Gable Assemblies You will need for this page: (QTY: 8) 8577 2 Left Gable 8576 2 Right Gable 6635 4 Roof Beam Bracket The gables are packed nested together and might be mistaken as on piece. Carefully separate them before continuing. Edge Trim (Plastic Piece) 8577 To avoid mishap on the sharp edge the edge trim must remain in place on the top edge of the gable until right and left roof panels are in place. 1 Apply edge trim to the top edge of the right gables and left gables.
Step 13: Gables/Braces You will need for this page: (QTY: 20) (QTY: 5) 9009 2 Gable Brace 6228 2 Track Sup. 1 Lift and fasten a right and left gable, under angel at corner, to the door track with screws. 2 Join the left and right gables together with a gable brace using a bolt in the second hole from the bottom only. 31BP Assemblies needed: • • Left Gable Assemblies (2) Right Gable Assemblies (2) Hint: On the front gable, leave out 2 screws closest to center gable leg.
Step 14: Roof Beam/Braces You will need for this page: Assemblies from Step 3: • • (QTY: 12) 1 2 Main Roof Beam Assembly (1) Single Roof Beam Assemblies (2) Seal the gap between the Gables using the weather stripping tape as shown. Do this at both ends of the building before installing Roof Beams. Position the Roof Beams as shown below and install using two (2) bolts and nuts per side. Install the Main (center) Beam first.
Step 14: Continued You will need for this page: (QTY: 4) 33BP 9204 2 Beam Brace In the front, attach the Roof Beam Brace to the Track Support with one (1) bolt and nut as shown and rotate to align with Roof Beam. Secure to Roof Beam with one (1) bolt and nut as shown in the second hole. 3 In the rear, attach the Roof Beam Brace to the Gable with one (1) bolt and nut as shown and rotate to align with Roof Beam. Secure to Roof Beam with one (1) bolt and nut as shown in the first hole.
Roof Install Prep Page 34BP Use the information on this page to complete steps 15 thru 18. If Roof Beam holes do not line up with Roof Panel holes, shift the building from left to right. If this does not help, your building may not be level. Shim the corners until holes line up. Measure the building diagonally again to make sure the building is square. The building should be square at the base and at the top. This will make roof panels fit better and holes will better align.
Step 15: Right Roof Panel 35BP You will need for this page: (QTY: 8) Right Roof Panel (QTY: 6) 1 Secure the first Right Roof Panel to the Main Roof Beam by placing screws with washers in holes #1 - #4. Fasten the holes in order. 2 Fasten Panel to Gable by placing bolts through holes #5 - #10. 3 Secure the Panel to the Lower Roof Beam by placing screws with washers in holes #11 - #14. Repeat for other three End Panels.
Step 16: Roof Assembly You will need for this page: (QTY: 32) (QTY: 6) 1 9087 Left Roof Panel 1 Install a left roof panel at the left rear corner of the roof. 2 Install two roof panels in the sequence shown on previous page. Follow fastener sequence while fastening roof panels. 7743 2 6869 1 Ridge Cap Roof Panel FASTEN TO RIDGE CAP (NEXT TWO PAGES) 7743 FASTEN TO ROOF BEAMS WITH SCREWS Narrow roof panel rib (with bead on it) is always overlapped by wide rib of adjacent panel.
Step 16: Continued You will need for this page: (QTY: 16) 7743 2 Roof Panel (QTY: 4) 6868 1 Ridge Cap Continue to apply weather stripping. 6 Install two roof panels as you unroll the weather stripping tape, and press it down, install the seconde ridge cap overlapping the first ridge cap. Align the holes and fasten using bolts and nuts. If roof beam holes do not line up with the roof panel holes, shift the building from left to right. If this does not help, your building may not be level.
Step 16: Continued You will need for this page: (QTY: 72) 9087 1 Right Roof Panel Left Roof Panel (QTY: 20) 9086 1 38BP 7743 2 Roof Panel Continue to apply weather stripping. 7 Install two roof panels, the left roof panel, ridge cap and right roof panel on the front of the roof as before. 8 Fasten the lower end of the panels to the side wall angles using screws and washers. 9 Finish weather stripping the roof and cut the tape just past the end of the roof. Fold end of tape under roof edge.
Step 17: Roof Trim You will need for this page: (QTY: 4) (QTY: 8) 6014 2 (QTY: 4) Side Trim 39BP 6015 4 Side Trim 2 Trim Cap (L) 2 Trim Cap (R) 2 1 Slide Peak Cap legs under Ridge Cap and secure with two (2) bolts and nuts. Peak Cap Position Roof Trim as shown below and secure with screws. Do not fasten the last screw on each end. Pay close attention to where the Left and Right Roof Trim pieces are located. 2 3 Position the Roof Trim Caps as shown below and secure with a screw.
Step 18: Door Assembly You will need for this page: (QTY: 6) (QTY: 4) 3719 2 10483 2 Door 2 9202 2 Handle Brace Vert. Brace 40BP Handle Do not fully tighten the bolts that hold on the Door Handle until the Vertical Door Brace is in place. These steps will need to be repeated when assembling second door. Secure Door Handle and Handle Brace to Door with two (2) bolts and nuts. 1 Attach the Door Handle and Door Handle Brace to the Door with two (2) bolts and nuts as shown.
Step 18: Continued You will need for this page: Horiz. Brace (QTY: 6) 3 4 10497 4 4 10497 Door Guide Slide Horizontal Brace over Door edge and secure with one (1) bolt and nut in top and bottom. Secure the Door Guides and Lower Horizontal Door Brace as shown below. Repeat steps for second Door. Door Guide 10497 10475 6278 3719 10497 Repeat these steps for the other door.
Step 19: Door Install You will need for this page: 42BP Assemblies from Step 18: • • Right Door Assembly (1) Left Door Assembly (1) (QTY: 8) 1 2 3 From inside the building, place the bottom of the Door into the Front Floor Frame track at about the halfopen position. Door Slide Gable Door Track Rotate the Door forward until it is vertical and align the Door Slides with the Door. Door Insert two (2) Black Screws into each Door Slide as shown below. Repeat steps for second door.
ANCHORING OPTIONS... 43A IMPORTANT: • • • • If you have swing doors, they must hang and swing level before anchoring building. Anchor your building at this time. See below for details on anchoring. If you have purchased a Floor Frame Kit, you should install it at this time. Please take a moment to ensure that the building is installed in accordance with these instructions and with all applicable regulations.
CARE & MAINTENANCE... 44A Exterior Care: For a long lasting finish, clean and wax the exterior surface. We recommend washing with a mild soap solution. DO NOT use power washing to clean your shed. Using a spray automotive type wax periodically on the exterior is highly recommended if you are in a high humidity or coastal climate region. Combustibles and corrosives must be stored in air tight containers designed for chemical and/or combustible storage.
ARROW ACCESSORIES... ROOF STRENGTHENING (heavy snow load) KITS Extra roof beams and gable braces designed for added protection against heavy snow accumulation. Increases the strength of your roof. ANCHOR KITS BEFORE 45A FLOOR FRAME KITS MODELS FB47410, FB5465, FB106-A, FB109-A and FB1014-A AFTER Model No. AK4 A simple floor frame system made of heavy-duty, hot-dipped galvanized steel. Use as base for plywood, sand or stone.
ASSEMBLY NOTES 46 46A
ASSEMBLY NOTES 47 46A
ASSEMBLY NOTES 48 46A