Hint: Coverage of 100% Solids Epoxy: When applied to a smooth/dry surface, coverage is approximately 300
sq.ft per 3 gallon kit of 100% solids epoxy. Coverage calculated @ 25-30 mils thickness. This is equivalent to 4
layers of standard floor paint. Topcoating adds an additional layer of protection and thickness.
B. PRODUCT APPLICATION
1. Pour the epoxy on the floor in a ribbon left to right. Have your flat squeegee ready to go
and spread it out evenly. You can swirl it around to create unique and custom looks and
impressions. You can use a variety of methods to achieve decorative results including
spraying, squeegeeing, etc. The epoxy will also change as it ‘levels out’. Spraying on
denatured alcohol from a hand pump sprayer can make the epoxy ‘dance and
swirl’, you would do this onto the spread epoxy. If you are using a second metallic color
add small amounts of it at this time and swirl into the first color to get the results you
want. Get as much of your mixed epoxy on the floor as fast as possible as the floor is
cooler and this will slow down the curing process and give you more time to work. Keep
mixed epoxy cool and in the shade, out of sun and heat.
2. Once you have achieved the look you want, let the metallic epoxy cure overnight.
3. TOPCOAT MUST BE APPLIED THE FOLLOWING DAY ONCE FLOOR IS
COMPLETELY DRY WITHIN THE RECOAT WINDOW OF UP TO 48 HOURS.
ℹ
Hint: Do not leave mixed material in the bucket or in the sun for extended periods of time.
ℹ
Hint: Do not use a roller pan for the epoxy step. Pour the mixed materials directly to the floor as the floor is
always cooler than the air and it will extend working times.
ℹ
Hint: Do not apply the topcoat until the floor is fully cured. You can press your finger to the epoxy and if you can
see your finder print please allow more time for the floor to cure
7. THIRD LAYER: 1-PART MILITARY TOPCOAT APPLICATION
The clear protective topcoat is a 1-prt moisture curing urethane. This product once applied over the
ArmorTallic 100% Solids epoxy is fully dry enough to walk on the next day (overnight, but can be
sooner depending on temperature or humidity conditions). TOPCOAT MUST BE APPLIED WITHIN
ONE DAY AFTER METALLIC EPOXY HAS BEEN PUT DOWN. IF IT HAS BEEN MORE THAN ONE
DAY SINCE THE EPOXY METALLIC COAT HAS BEEN APPLIED, THE SURFACE NEEDS TO BE
LIGHTLY SANDED BEFORE TOPCOATING CAN BEGIN. AFTER SANDING TACK WIPE THE
FLOOR WITH DENATURED ALCOHOL AND ENSURE TO NO DUST AND DEBRIS REMAIN.
Please note that use of any non skid additive will de-gloss the floor so you may not want to use it, but
this can make the floor very slippery if wet or greasy. Armorgrip is supplied with this kit. It is a
micronized polymer that gets mixed into the topcoat and will be invisible to the eye when dry. This
however can slightly de-gloss the floor and is not mandatory to use to achieve success; however we
highly recommend using it to ensure there is enough traction on the floor when it’s dry.
Use 1 package of Armorgrip per gallon of topcoat. Slowly pour the contents of the non-skid into the
topcoat and mix well to thoroughly suspend in the mixture. THE TOPCOAT SHOULD BE APPLIED
WITH A ROLLER ONLY. DO NOT USE A SQUEEGEE AT ALL FOR THIS APPLICATION
ℹ
Hint: The non skid will settle while mixed in the topcoat, so periodic stirring to re-suspend the nonskid is required during
the application process to assure uniform application of the anti-slip aggregate.