Use and Care Manual

INSTALLATION CHART
INSTALLATION
TIMELINE
DAY 1
DAY 2
DAY 3
DAY 4
PREP FLOOR
ACID ETCH. WAIT
FOR FLOOR TO DRY
OVERNIGHT
PRIME
WAIT AT LEAST 6
HOURS FOR FLOOR
TO DRY OR
OVERNIGHT
METALLIC
EPOXY COAT
WAIT FOR FLOOR TO
DRY OVERNIGHT OR
24 HOURS
TOPCOAT
WAIT FOR FLOOR TO
DRY OVERNIGHT OR
24 HOURS
DRY TIMES
DRY TO TOUCH
12-24 HOURS
FOOT TRAFFIC
24 HOURS
LIGHT
EQUIPMENT
48-72 HOURS
VEHICLE
TRAFFIC
5-7 DAYS
APPLICATION
TEMPERATURE
50-90°F
LOWER TEMPERATURES
WILL INCREASE DRY
TIMES
RELATIVE
HUMIDITY
80% OR LESS
ARMORTALLIC EPOXY SYSTEM
3