Technical information

17
installation
Clamp
Seal
Screws
Fitting the 5” Flue
(Ø 80 / 125 Horizontal/vertical)
Once the boiler has been positioned on the wall, it is necessary
to insert the Ø80/125 adaptor (Fig. 5) for both horizontal and
vertical ue runs into the boiler ue socket (not supplied with
ue kit - Part No 3318095).
Push the adaptor onto the boilers ue connection, grease the
seals then add extensions or elbows as required, secure the
adaptor, using the clamp and screws provided.
To t extensions or elbows it is rst necessary to ensure that the
lip seal is tted correctly into the inner ue, once veried, it is
simply necessary to push them together, no clamps are neces-
sary to secure the ue components.
Before proceeding to t the ue, ensure that the maximum
ue length has not been exceeded (See the tables) and that all
elbows and bends have been taken into consideration, the ma-
ximum ue length is 10 metres, for each additional 90° elbow 1
metre must be subtracted from the total ue length, and for each
45° 0.5 metres must be subtracted from the total ue length (the
height of the vertical adaptor and a 45° bend can be seen in Fig.6
and a 90° bend in Fig. 7).
Note: DO NOT cut the vertical ue kit.
180 mm
Fig. 4
Fig. 5
Fig. 6 Fig. 7