a. For a Select Downstream Power setting of High or Medium verify that the
Downstream Transmit Power setting indicates 10 or greater .
b. For a Select Downstream Power setting of Low verify that the Downstream
Transmit Power setting indicates Below 10.
Set the Hub Management Mode
)Referring to the Real Time Monitor Information table on the Arcwave MIB page of the user
interface:
1. Enter Title, if desired, otherwise it defaults to the MAC address of the ECM.
2. Set the Alarm Destination IP address, if desired.
3. Choose the method for managing the Hub by setting the Select Control Mode:
If Control via HTTP is chosen, then the Hub can be managed remotely over the cable network or
locally using the Ethernet port using the embedded a PC and the HTTP-based user interface.
If the Control via SNMP is chosen, then the Hub can be managed remotely over the cable network
using SNMP.
CPE installation
)Install the CPE mounting hardware (not supplied by Arcwave) per the manufacturer’s
recommended procedures and in accordance with the National Electric Code and local
ordinances.
Note: The CPE accommodates a mounting pipe with of 1-1/4” to 2-3/8” in diameter and the CPE
and mounting pipe require a minimum of 12 inches clearance on all sides for optimal performance.
Note: The CPE should be located as close to the edge of the building nearest the hub as possible.
When the CPE is mounted towards the middle or back of the building, the incoming wireless signal
may be reflected by the rooftop impairing the performance of the link. The CPE must be placed
high enough on the rooftop to provide the required Fresnel zone clearance (Fresnel zone =
blockage free zone).
Affix the CPE mounting mast
)Referring to Figure 4-3, loosen the "Side/side alignment bolts and slide the CPE over the
mounting pipe. Visually align the CPE in the direction of the Hub and snug the side/side
alignment bolts to hold the CPE in place.