User's Manual

Ground lead lug installed
Pipe clamps installed
Figure 5-4: Hub Transceiver Bracket Detail
Bundle the three cables (2 x RG-6, power) with suitable (UV rated) tie wraps and secure to the
mounting structure in a manner to prevent rainwater from flowing down the cable and into the
cable access opening in the rear weather cap. Figure 5-5 illustrates a typical installation. Be
certain to provide a drip loop if the cable bundle is routed upward.
In the case of a single sector, single Hub Transceiver installation, route the bundle of three
cables to the base station indoor equipment room. Take care to leave suitable drip loops and
bond the shields of the RG-6 and power cables to ground per local codes and installation
practices.
If the base station site is multi-sector (two or more collocated Hub Transceivers), route the
bundles of three cables to the equipment room as above. If an Outdoor Junction Box (OJB) is
to be employed in the installation, route the cables to the OJB.
June 2003 Page 5-4