Installation Guide

TYPICAL FREESTANDING BATHTUB INSTALLATION PROCEDURE
Before you start:
• Ensure that the floor is even.
• The wate-overflow fitting is supplied with the product, however other accessories like the slip joint and adaptors are
not included and must be purchased seaparately.
• Because of the technical features of the product, it should be used only with the supplied waste-overflow or specific
3rd party models that have been tested and approved by us.
• Handgrip application for our product is not available.
• The bathtub must be carried in the upside-down position. Do not lift or support the bathtub by the panels.
• Place the bathtub by raising it up 3½” with 4x4 peices of lumber so you can have access from the bottom of the
bathtub.
• For cleaning of the acrylic bathtub look at our Acrylic Bathtub Maintenance Manual.
INSTALLATION SEQUENCE
• Picture 1-2: the bathtub must be carried upside-down. It must never be
carried by its panel.
• Picture 3: the waste-overflow fitting is pre-installed with the bathtub at
the factory. The corrugated extender must be removed and discarded
unless there is absolutely no other way to complete the installaton.
The waste pipe/p-trap connection must be made directly to waste/drain
outlet located at the bottom of the tub.
1 2 3