Instructions / Assembly
— 2 —
Customer Service: 800-945-2726
Installation Data
6030SPANL/R, 6030SPANML/R,
6030STUBL/R, 6030STUBML/R
1. Review job print and Aquatic rough-in dimensions; verify all key
dimensions against actual job conditions.
2. In remodeling, if necessary, add studs at each end to provide a
vertical nailing surface for the side nailing flanges of bath fixture
product.
3. Make sure framed-in framing pocket is of proper size, square and
plumb; check floor for level. Some shimming between the stud
frame and fixture may be required.
4. If fire-rated framing pocket is required, approved finish material
must be in place prior to unit installation to meet fire safety
requirements of local building code and/or FHA/HUD Minimum
Property Standards.
NOTE: Finished framing pocket must have interior dimensions
shown on rough-in diagram to permit installation of unit.
5. Foundation materials are not required for these units.
6. DO NOT install the product over open floor joist. Shimming may
be required for additional support, if subfloor is uneven.
7. Tubs require a 6” x 12” floor opening for the 2” IPS drain
connection (See diagram 1 for location). Shower pans require a
6” diameter floor opening.NOTE: Be sure floor opening location
matches left-hand or right-hand bath fixture drain location.
8. Make sure all plumbing is complete and to code.
9. To avoid obstruction, make sure that supply lines and valve
plumbing do not project into framing pocket during the installation
process.
10. To prevent scuffing while installing unit, cover the floor of the unit
with a piece of cardboard or other protective material.
11. Fasteners for:
Wood framing – 1 1/2” galvanized roofing nails or #10 x 1
1/2” self-tapping washer head screws.
Concrete or block walls – 1” concrete nails and nailing tool.
Steel studs (18 ga.) – drill flanges and studs with 5/32”
carbide bit and use #12 x 1” sheet metal screws.
Pre-Installation Planning
*Please read ALL installation instructions completely before beginning.
Check dimensions. NOTE: If you’re adding additional accessories such as
a grab bar–additional framing or backing may be needed for support.
Pre-install unit to ensure framing pocket is plumb, square, and a level installation can be
achieved. (See steps 2 and 3.) Adjust framing as needed – shim where necessary.
6"x12"
AA
AA
C
C
DD
B
B
11
Models A B C D
6030SPAN
6030SPANM
60
1
⁄8” 31
1
⁄4” 8
1
⁄2” 14
1
⁄2”
6030STUB
6030STUBM
60
1
⁄8” 31
1
⁄4” 2” 13
7
⁄8”
Pre-Installation Instructions
*Review Tech Data at aquaticbath.com for more detail.
NOTE: 6030SPAN is shown for illustrational purposes
Level and mark all sides. Front apron should be firmly on the floor.
NOTE: If unit is not level, the joints and seams will not align properly.
33
Lift and place the base into framing.
22