Install Instructions
LOCATION CONSIDERATIONS
TOP VIEW
FILTER
MINIMUM
CLEARANCE FOR FILTER
(EITHER SIDE)
15"
6" MINIMUM CLEARANCE
FOR PROPER AIR FLOW
ELECTRICAL SERVICE
ACCESS THIS SIDE
6 FT. POWER CORD
FIGURE 6 – Filter Access Clearance
90-1840
• Allow sufficient clearance for filter removal and
to prevent airflow obstruction
• Electrical service access will require the removal
of the side panel shown. Allow sufficient space
for service on this side of the unit.
0.38" MIN
2.00" MAX
3/4" DRAIN
BUBBLE LEVEL
INSTALLATION
LEVELING
DUCTWORK INSTALLATION
The feet can be adjusted to level the unit and
accommodate drain fittings and secondary
condensate pans as required. Refer to top mounted
bubble level and adjust feet until bubble is within
the outer circle. Leveling is required to ensure
proper drainage from the dehumidifier. See
Figure 7.
Adding 5-10 feet of insulated ductwork to the inlet and outlet of the dehumidifier will ensure dehumidified air is circulated throughout the crawl
space and will reduce the noise level of the dehumidifier. Point the inlet and outlet ducts in opposite directions to minimize recirculation of
dehumidified air.
• Make sure there are no bends in the ductwork coming off the outlet for a minimum of 4”. This will ensure that the ductwork will not interfere
with the backflow damper function.
• Maximum recommended total duct length is 100 feet.
• To avoid pulling in dirt and other particles, do not lay intake duct on the floor of the crawl space.
FIGURE 7 – Level the Unit
90-1885
5