Chiller filling procedure 
1.  Check valves in your application are open 
2.  Remove lid from the coolant reservoir 
3.  Fill with Hexid to within 40mm (1½ inches) of the tank rim. 
4.  Switch the unit on. 
5.  Wait while the fluid level drops in the tank. 
6.  Switch the unit off. 
7.  Repeat steps 3 to 5 until all of the air has been purged from the system. 
8.  Top up to a level 40mm (1½ inches) below the tank rim. 
9.  Check the inlet and outlet connections, and the inside of your application carefully for 
leaks. If no leaks are found, the system is ready to be run. 
Warning: Always isolate the chiller from the electrical supply when filling the tank. 
Operator 
section 
Component identification photograph, KT series 
(model shown is KTR) 
Mains inlet 
Coolant reservoir lid 
Neon 
On / Off switch 
Lifting handle (front) 
Coolant inlet connection 
Coolant outlet connection