Instruction manual
KT series chillers – Installation and Operation manual
Issue 7.0 Page 8
Chiller filling procedure
1. Check valves in your application are open
2. Remove lid from the coolant reservoir
3. Fill with Hexid to within 40mm (1½ inches) of the tank rim.
4. Switch the unit on.
5. Wait while the fluid level drops in the tank.
6. Switch the unit off.
7. Repeat steps 3 to 5 until all of the air has been purged from the system.
8. Top up to a level 40mm (1½ inches) below the tank rim.
9. Check the inlet and outlet connections, and the inside of your application carefully for
leaks. If no leaks are found, the system is ready to be run.
Warning: Always isolate the chiller from the electrical supply when filling the tank.
Operator
section
Component identification photograph, KT series
(model shown is KTR)
Mains inlet
Coolant reservoir lid
Neon
On / Off switch
Lifting handle (front)
Coolant inlet connection
Coolant outlet connection