Specifications

Operation
19
Disassembly of the EK Siphon
Danger of Accidents!
Dismantle the EK Siphon only with unpressurized
vessel.
1. Close the pressure build-up valve (7).
2. Close the filling/withdrawal valve (3).
3. Detach the connected withdrawal line from the EK Siphon.
4. Open the waste gas/overflow (1) valve for relieving the
pressure of the vessel.
5. Loosen the wing screw (8) and remove the straining ring
(9) from the unpressurized tank.
6. Remove the EK Siphon (2) by pulling it out carefully from
the top and deposit it carefully.
7. Loosely insert the transport stopper.
Note
Avoid any heavy mechanical strain.
Do not carry out any assembly and disassembly
while the vessel is cold.
Assembly of the Transfer Hose
1. Screw the union nut (3) onto the connecting screwing (2) of
the filling/withdrawal valve (1).
2. Tighten the union nut (3) by means of an open-jawed
wrench; in doing so retain the hexagon (2) with a wrench.
3. If necessary, tighten the union nut (3) in cold condition.
Caution !
Observe safety instructions.
Use filling line with safety valve and pressure relief.
Wear gloves and safety glasses.
Protect the vessel from rolling away, tumbling down
and damage.
The pressure in the supply vessel must not be
higher than 1,3 bar
Note !
Additional aggregates for filling and withdrawal have
to be adapted to the operating conditions of the
vessel.
Filling has to take place outside or in a sufficient
ventilated room
Risk of suffocation
5.3 Assembly of the Transfer
Hose
5.4 Filling of the Vessel