19.0 TEMPORARY CONTROLS AND FACILITIES
A. The Contractor is responsible for compliance with all NPDES regulations including submitting a
Pollution Prevention Plan, submitting a Notice of Intent, conducting maintenance and inspection
of controls, erosion and sediment controls and submitting a Notice of Termination.
B. As part of the Work, the Contractor shall be responsible for applying for, obtaining and
complying with all required dewatering permits. Contractor shall notify South Florida Water
Management District (SFWMD) prior to all dewatering activities. All dewatering shall meet
SFWMD requirements.
C. Contractor shall prevent erosion of soil on the site and on adjacent properties resulting from
construction activities, effective measures shall be initiated prior to commencement of clearing,
grading, excavation, or other operations. Contractor shall install silt barriers or screens to
capture sediments/solids from erosion.
D. Contractor shall perform dust and mud control operations to prevent construction operations
from producing dust and mud in amounts harmful to persons or causing a nuisance to persons
living nearby or occupying buildings in the vicinity of the Work. Use water or dust preventative
to control dust during dry weather. Take necessary steps to prevent the tracking of mud onto
adjacent streets and highways.
E. Contractor shall install all turbidity control devices required by SFWMD, if necessary.
Contractor shall notify SFWMD for inspection of turbidity control devices prior to any
construction activities.
20.0 STORAGE SITES
A. The Contractor may furnish, at his expense, properly zoned areas suitable for field offices,
material storage and equipment service, and storage. The Contractor shall maintain these areas
in a clean, orderly condition so as not to cause a nuisance in the area. The Contractor shall
restore the storage area to its original or better condition, with all its appurtenances, in kind, to
the satisfaction of the Engineer. Contractor is responsible for security of storage site.
21.0 CONTRACTOR’S SUBMITTALS
A. Contractor shall be required to submit, with a letter of transmittal to the Engineer, a minimum of
eight (8) copies of each checked and approved shop drawing, mix report, laboratory results, etc.,
where required in the specifications, Drawings or as appropriate, in lieu of the five (5) copies
specified in Article 6 of the General Conditions or as specified elsewhere in these Specifications.
Of the ten copies submitted, two copies will be returned to the Contractor for the Contractor’s
use. If the Contractor requires any additional approved copies, the Contractor shall submit
additional copies at the time of initial submission. Allow a minimum of two weeks from date of
receipt for review by the Engineer. Review of shop drawings will be general and will not relieve
the Contractor from any responsibility.
A. Contractor shall be required to submit, with a letter of transmittal to the Engineer, for review and
approval, eight (8) hard copies and eight (8) copies in CD format of each Operation and
Maintenance Manual for all equipment, regardless of the number of submittals specified elsewhere
in these Specifications.