Specifications
16721-4
11/21/2012 10:16 AM
3. Show layout, configurations, and terminations.
C. Manuals
1. Submit simultaneously with the shop drawings, complete operating and
maintenance manuals listing the manufacturer's name(s), including technical
data sheets.
2. Wiring diagrams shall indicate internal wiring for each device and the
interconnections between the items of equipment. Power requirements shall
be included.
3. Provide a clear and concise description of operation that gives, in detail, the
information required to properly operate the equipment and system.
D. Setup and Configuration
1. Provide the services of a qualified technician to perform all system setup,
modifications, upgrades or changes. Response time of the technician to the
site shall not exceed 4 hours.
2. Provide all hardware, software, programming tools and documentation
necessary to support the system. Work includes addition of devices, circuits
and camera zones.
E. Certifications
1. Together with the shop drawing submittal, submit a certification from the
major equipment manufacturer indicating that the proposed supervisor of the
installation and the proposed performer of contract maintenance is an
authorized representative of the major equipment manufacturer. Include
names and addresses in the certification.
1.04 GUARRANTY
A. All work performed and all material and equipment furnished under this contract
shall be free from defects and shall remain so for a period of at least one (1) year
from the date of acceptance. The full cost of maintenance, labor and materials
required to correct any defect during this one year period shall be included in the
submittal bid.
1.05 MAINTENANCE
A. Maintenance and testing shall be on a semi-annual schedule or as required by the
Owner and is not included with this contract. The contractor shall provide a