Specifications
16621-3
5. Install transfer switch and 480V distribution panel at specified location
inside control room.
6. Install conduit from disconnect to transfer switch inside control room.
7. Pull and terminate 3-phase AC power wiring from disconnect to transfer
switch.
8. Install conduits from Substation 6A to 350kW generator transfer switch.
9. Install conduits from transfer switch distribution panel to MCC5A.
10. Pull and terminate 3-phase AC wiring from substation 6A to 350kW
generator transfer switch.
11. Pull and terminate 3-phase AC wiring from transfer switch distribution
panel to MCC5A.
12. Install DC battery charger at specified location inside generator room.
13. Install 1 ½”conduit from generator to PLC-3 cabinet in control room.
14. Pull and terminate control wiring from generator to PLC-3.
15. Commission and test operation of diesel generator in accordance with
Engineer.
1.05 DAILY LOG: The Contractor shall maintain a detailed daily log of the
construction and testing operations activity for the duration of the project. The logs shall
be maintained in an organized ledger and shall give a detailed description of the daily
activity as well as daily starting and stopping points. The logs shall include a record of
all down time due to planned and unplanned activity and any other pertinent data as
may be required by the Engineer. All Contractor and Sub-Contractor activity shall be
recorded in a single log for submission to the Engineer. Two copies of the daily log
shall be submitted to the Engineer (or Engineer’s representative) on a daily basis.
1.06 AS-INSTALLED DRAWINGS: Upon completion of the work, the Contractor shall
supply the Engineer with accurate and reproducible as-installed drawings of all electrical
and mechanical installations. The drawings shall show conduit sizes, wire sizes,
electrical specifications and ratings, installed components, mechanical dimensions and
other information that may be required by the Engineer and regulatory agencies,
including deviations from the proposed construction details noted.
1.07 STANDBY TIME: The Owner may order the Contractor to stop operations so
that extra work not included in these Specifications, such as testing and additional data
collection, can be performed. The Owner and Engineer shall schedule the request so it
causes a minimum of delay. The Contractor shall be reimbursed at hourly rates listed in
the unit price bid form. All standby time for which extra payment will be made shall be
approved by the Engineer in writing in advance.