Specifications

16621-2
attendance shall be performed during daylight hours (7:00 a.m. to 7:00 p.m.), unless
prior approval from the Engineer has been obtained. It is understood that certain tests
may extend into the evening and cannot be stopped when in progress.
Contractor will perform work and testing as to minimize facility down-time. At no
time will fewer than three (3) gas turbine packages be operational without prior
approval from Owner and Engineer.
1.04 OUTLINE SPECIFICATION FOR WORK: After a Contractor has been selected,
a pre-construction meeting will be held at the Plant prior to commencement of work.
The following items represent and identify the general outline of work to be performed
by the Contractor; additional details regarding specific work items are included in
subsequent Parts of this Section.
A. Site Preparation, Mobilization and Demobilization:
1. Review current site conditions and record as necessary.
2. Mobilization to site.
3. Review of schedule and down-time plan.
4. Inventory of equipment.
5. Coordinate work-scope with Owner and Engineer.
6. Demobilization
B. Replacement of Existing 480V Substation
1. Isolate temporary power feed from existing emergency diesel generator to
MCC5A.
2. Operate emergency diesel generator to provide power to MCC5A.
3. Disconnect 4160V feed to Substation 6A.
4. Remove existing Substation 6A.
5. Install new Substation 6A (equipment as specified).
6. Commission and test as required.
C. Installation of New 350kW Diesel Generator and Transfer Switch
1. Install diesel generator and electrical disconnect at specified location
inside emergency power plant.
2. Install liquid fuel line from supply manifold to generator.
3. Install exhaust piping.
4. Install cooling system ductwork.