Specifications
01001-3
07/26/10
L:\wpb_\wpb_emp1\W1200.13\p.m. Project #1\01001-072610 Noboil.doc
B. When the Bid Form includes a separate pay item for Mobilization, partial payments will be made
in accordance with the following:
Allowable Percent
Percent of Contract Price of the Lump Sum
Less Mobilization Earned
Price of Mobilization
5 25
10 50
25 75
50 100
The standard retainage will be applied to these payments. Previous payments for Mobilization
and unpaid amounts on Allowances will not be considered in calculating the percent of the
Contract Price earned. Payments will be made in stepped increments as shown and will not be
interpolated between steps.
C. When the Bid Form does not include a separate item for Mobilization, all Work and incidental
costs specified as being covered under Mobilization is to be included for payment under the
several scheduled items on the Bid Form, and no separate payment will be made therefor.
9.0 MAINTENANCE OF TRAFFIC
A. In the Contractor's use of streets and highways for the Work to be done under these
Specifications, conform to all Municipal, County, State and Federal laws and regulations as
applicable. Provide, erect and maintain effective barricades, warning lights, and signs on all
intercepted streets or highways for protection of the Work and safety of the public. All
barricades or obstructions which encroach on or are adjacent to the public rights of way should
be provided with lights which are illuminated at all times between sunset and sunrise.
B. Contractor shall schedule Work to cause minimum disturbance of normal pedestrian and
vehicular traffic and be responsible for providing suitable means of access to all public and
private properties during all stages of the construction. Other than for an emergency safety
condition, the Contractor must contact the Owner and Engineer for approval prior to completely
blocking off any street to vehicular traffic during construction. Contractor shall provide written
notification to emergency, police, fire, and other appropriate agencies at least 24 hours in
advance of new work or changed work.
C. Maintain traffic in accordance with Section 102 of the Florida Department of Transportation
Standard Specifications for Road and Bridge Construction, 2007 Edition, except as follows:
1. Contractor shall be responsible for preparing a Maintenance of Traffic plan. Contractor shall
submit a Maintenance of Traffic Plan for Owner or roadway authority (City, County, D.O.T.)
review.
2. The Maintenance of Traffic plan must be prepared by a person who is certified by an FDOT
certified school or an engineer licensed in the State of Florida.
3. When the Bid Form does not include a separate item for Maintenance of Traffic, the costs
are to be included for payment under the several scheduled items on the Bid Form, and no
separate payment will be made.
10.0 PLACING EQUIPMENT INTO SERVICE
A. Do not operate or place into service or energize, electrical and mechanical equipment until
approved by the Owner and Engineer. Such approval may be granted only after all interested
parties have been duly notified, have given approval for placing the equipment into service, and