Specifications

16201-12
L:\wpb_\wpb_emp1\W1200.13\p.m. Project #1\SECTION 16201-Indoor Generator and ATS.doc
A. Unit shall be installed in accordance with Manufacturer’s instructions.
3.02 TESTS
A. The unit shall be tested at rated frequency and voltage.
B. Following installation, the following tests shall be performed by the
system manufacturer’s local dealer representative(s) in the presence of the
Engineer:
1. Pre-start checks:
a. Oil level
b. Water level
c. Tank fuel level
d. Battery connection and charge condition
e. Engine to control interconnects
f. Engine generator intake/exhaust obstructions
C. Supplier shall provide onsite operation tests
1. Load – One hour operation at 80% of full load rating. Two hours
operation at 100% of full load rating. After the first half hour
stabilization period at full load, the following shall be recorded at
fifteen minute intervals:
a. Voltage, amps and frequency.
b. Fuel pressure, oil pressure and water temperature.
c. Exhaust gas temperature at engine exhaust outlet.
d. Ambient temperature
e. Kilowatts
f. Power factor
g. kVARS
h. Generator temperature