Specifications

PIP ELSGS01
COMPLETE REVISION
Design and Fabrication of High-Resistance Grounding System (600 Volts or Below) July 2004
Page 10 of 11 Process Industry Practices
4.14.3 Instructions for testing the power system to determine its normal capacitive
charging current shall be provided.
4.14.4 Drawings submitted for approval shall include factory default setting of taps.
4.14.5 Documentation of the type and quantity shown in Table 1 and the
purchaser’s data sheet, PIP ELSGS01D, shall be provided.
4.14.6 One reproducible set of drawings and the specified number of copies of all
documentation and operating manuals as indicated on the purchaser’s data
sheet, PIP ELSGS01D, shall be provided.
4.14.7 Unless otherwise specified on the purchaser’s data sheet, PIP ELSGS01D,
format for reproducible drawings shall be CAD convertible .dxf electronic
format.
TABLE 1 - DOCUMENTATION REQUIREMENTS
A B C D DESCRIPTION
X X X Detailed bill of material
X X X X General layout of equipment, showing all dimensions,
weights, location, and outline drawings, showing the final
assembled configuration
X X Connection wiring diagrams for all electrical equipment
X X X Single-line, 3-line, and control schematic diagrams
X Certified test reports
X(1) Installation, operation, and maintenance manual
X Final as-built drawings
X X Recommended priced spare parts list
NOTES:
A. These documents shall be furnished with proposal.
B. These documents shall be furnished for purchaser’s review and authorization
to proceed before fabrication.
C. These documents shall be furnished as part of the final certified document
submittal.
(1) Equipment shall be shipped with one set of installation, operation, and
maintenance manuals.
D. The final as-built documents shall be furnished within 2 weeks following
shipment.