Datasheet

System Start-Up Procedure
Symmetra
®
PX 10-80 kW, 208V – Operation & Maintenance Guide – 990-1430 REV01 33
Press the down key and then the enter key to select Status. Verify that all power, battery
and intelligence modules are detected by the system and are functioning correctly by scrolling down
and reviewing all status screens. Please note that the intelligence modules are monitored under
the “Miscellaneous” Status Screen (submenu under Status).
From the Control Menu, choose Turn Load On.
Load On LED should now be lit.
If you are using a network connection, please refer to the enclosed Product Manual CD.
If a problem is reported, ensure that the system component in question is correctly
installed. If the problem persists, refer to Basic Troubleshooting.
The UPS is now ready to support the load equipment.
For further operation, PowerView features, and configuration, see Basic Operation
Guide and Product Manual CD (shipped with unit) and visit our website: www.apc.com.
Bat Voltage: 218V
Bat Capacity 100.0%
Runtime: 01hr 30min
32 Batts, 00Bad
Typical Status Screen
Turn Load On
Do Self Test
Simulate Power Fail
Graceful Reboot
Control Menu Screen
UPS Load is ON.
Confirm Menu Screen
LOAD ON
ON BATT
BYPASS
FAULT