9Smart-UPS® VT, MGE™ Galaxy™ 3500 10-40 kVA 400 V Installation
Mount the MBP to the wall
Note: APC strongly recommends mounting the MBP to a minimum 20-mm thick plywood
board or similar solid backing that has approximate dimensions of 660mm (26in) L × 600mm
(24in) W.
Mount the plywood (or other backing) to the wall using appropriate hardware for the type of wall used.
See “Site Planning” on page 6 for guidelines on choosing where to mount the unit.
Measure and mark the four (4) mounting hole locations on the backing. Refer to the following table for
the correct horizontal and vertical spacing between each of the mounting holes.
Drill starter holes in each of the four (4) marked locations.
Lift the MBP and position it against the backing, lining up each of the four (4) mounting holes with each
of the four (4) drilled starter holes.
Note: APC recommends that two people mount the MBP to the wall—one person to lift and
hold the enclosure, and a second person to secure it to the wall.
Using a metric wrench, screw four (4) 6-mm hex-head lag bolts (each 25-mm long), along with four flat
washers, into the enclosure’s mounting holes. Tighten until rigid.
Internal cable connections
The MBP ships from the factory with the internal wiring between the Q1 input switch and the Q3 bypass
switch, as well as the Q3 to Q2 busbar connections, completed. Prior to beginning external wiring, verify
these internal connections as shown in the following illustration.
KVA Vertical Spacing Horizontal Spacing
10-20 240mm (9.45 in) between holes 240mm (9.45 in) between holes
30-40 380mm (14.96 in) between holes 330mm (13.00 in) between holes