Specifications

StarttheSystemafterTotalPowerOff
1.Settheupstreamutility/mainspowertothe
ONorLOCKEDINposition.IftheUPShasa
dualmainssupply,setbothsuppliestotheON
orLOCKEDINposition.
2.SettheDCDISCONNECTswitchtotheON
positiononallXRBatteryEnclosuresandthe
PDU-XR(ifapplicable)andonthemainframe
(onlyPX48).
3.SettheQ1switchtotheONposition.
XRBatteryEnclosures/PDU-XR
4.SettheSYSTEMENABLEswitchontheUPS
totheONposition.
Note:Waitapproximatelytwo
minutesforthesystemtostart.
4
5.SettheQ5breakertotheONposition(if
applicable).
Note:TheH2LEDnexttotheQ2
switchwillturnon,indicatingthatit
issafetooperatetheQ2switch.
6.SettheQ2switchonthePDU,PDU-XRor
theexternalmaintenancebypasspaneltothe
ONposition.
7.SelectUPSandpressENTER.
UPSAlarms
PowerDistLog
SwitchGearAdmin
EnvironmentHelp
8.SelectUPSPowerControlandpressENTER.
UPSPowerControl
UPSStatus
UPSTests&Diags
UPSConfiguration
9.SelectTurnUPSOnandpressENTER.
TurnUPSOn
UPSOnIntoBypass
10
Symmetra™PX48,96,and160kW400V100kW208VOperation
990–3015E-001