Specifications
System Operation
38 40kW InfraStruXure PDU—Operation and Configuration
5. Set the UPS DC Disconnect breaker to ON,
and then set the UPS System Enable switch to
ON.
6. If applicable, set the XR Battery Enclosure DC
Disconnect breaker to ON.
When the System Enable switch is placed in the ON position, the Startup screen appears on the
display interface of the Symmetra PX UPS.
The top-level status screen appears on the display interface. This may take up to 30 seconds.
PowerView RM
Rev: 000 English
Please wait...
Fuel%
Load%
Runtime:
||||||||||||
|||
1hr 2m
In 400V out000V 50Hz