Specifications
Table Of Contents
- General Information
 - Component Identification
 - Installation
 - Warranty
 

InRow Fluid Cooled RD Installation20
Mechanical Connections
Liquid piping
Note: Install all piping in accordance with applicable industry guidelines as well as local and 
national codes and regulations.
Piping for the liquid lines is located in the cabinet. Route them through either the top or bottom of the 
cabinet and connect them to to the water inlet and water outlet fittings. Use the provided gaskets for all 
connections and insulate the liquid lines with the provided insulation. See “Install kit” on page 5.
Condensate pump
The condensate pumps 
 (air cooled equipment shown) 
are factory-wired and piped internally to the condensate 
pan. The pumps are capable of moving liquid a 
maximum of 15.2 m (50.0 ft), which may include a 
maximum lift of 4.9 m (16.0 ft) as measured from floor 
level. For example, if your lift is 3 m (10 ft), you only 
have 12.2 m (40.0 ft) of usable run remaining. The 
pumps also use an on-board condensate high level float 
switch, which is wired into the alarm input for local and 
remote alarm capabilities.
Condensate pump drain connection. Sufficient 
PVC drain line 
 is supplied to route the drain to the 
outside of the equipment. Provide additional drain line at 
installation to allow routing to a remote drain.
Warning: Do not exceed the lift or the run length of the drain system.
na2670a
Warning: To prevent equipment damage 
from condensate, do not leave the 
condensate drain line coiled inside the unit. 
Route the condensate line out the top or 
bottom of the unit as shown on the next 
page.