7Pumped Refrigerant System Operation and Maintenance
Start-up Inspection Checklist
The start-up inspection ensures that the equipment is operating properly after the initial start-up. This
inspection verifies that all modes of operation are working correctly and that the equipment is ready for
normal operation.
See “Start the RDU” on page 1 for startup information.
Final Inspection Checklist
The final inspection verifies that the system is clean, the installed options work properly, and the start-up
form is sent to APC.
While the equipment is operating, ensure that:
5
The unit is free from malfunctions, including chilled water leaks, or other irregularities, in each mode of
operation.
5
Both the primary and secondary power inputs can supply power to all functions in the equipment.
5
A pump is operating.
5
Air filters in CMs (RA only) are clean and free of debris. Replace air filters with APC air filters only.
Ensure that:
5
The system is clean and free from debris.
5
Packaging materials are disposed of properly.
5
The start-up form was completed and sent to APC.