Mechanical inspection
The mechanical inspection verifies that all mechanical components and connections are
secure.
NOTICE
PIPING INSTALLATION
Failure to properly install piping may result in improper cooling unit operation.
Failure to follow these instructions can result in equipment damage.
Ensure that the:
Mechanical connections are tight.
Fans are turning freely and the blades are not distorted or bent.
Pipe fittings are tight.
Spray nozzles are free of debris and there are no blockages.
Water supply valves are open. Water flow is correct based on the performance requirements of
the system.
Field-installed traps and piping are in accordance with the installation manual. Strainers are in
place in the water supply loop. Proper piping practices have been followed.
Piping is adequately supported.
Field-installed service valves are open.
Piping is properly insulated.
Covers and guards are in place.
Drain line is at least the size of the drain connection.
Drain line is installed properly and has an air gap installed.
Water supply and drain joints are tight and do not leak.
Supply water piping has freeze protection.
Mechanical connections are tight, including compressor rotolock connections.
All doors hinge freely and latch properly.
All major components (fans, motors, dampers, and coils), attachments, and mountings are free
of damage.
There are no signs of refrigerant leakage from any coil or piping.
Outdoor air intake openings are not blocked and free of any debris.
Condenser coils at each Module are not damaged or obstructed.
Ductwork is correctly mounted and sealed.
Vibration damper pads for Frame and ductwork are properly installed.
TANDEMLOC clamp connectors are properly tightened.