Basic Installation Procedures
14 InfraStruXure for Wiring Closets and Computer Rooms
3. Level the enclosures.
Leveling feet are attached under the enclosure at the corners. The leveling feet can help provide
a stable base if the selected floor space is uneven, but cannot compensate for a badly sloped
surface. To level the enclosure:
a. Fit the 14-millimeter end of the open-ended wrench
(provided) to the hex head just above the round pad
on the bottom of a leveling foot. Turn the wrench
clockwise to extend the leveling foot until it makes
firm contact with the floor.
b. Repeat step a for each of the remaining leveling
feet.
c. Use a level to determine which feet need further
adjustment to level the enclosure. Adjust as
necessary.
Install the UPS
Install the UPS in the bottom of the selected rack or
enclosure. (See “Site Planning” on page 10 for sample
configurations.) If you have a Symmetra RM UPS or a
Symmetra LX UPS, install the power and battery
modules after you install the UPS in the rack.
Install the Rack PDU Extender
The Rack PDU Extender is used primarily with
the Symmetra LX UPS and the NetShelter VX
Enclosure. It snaps into the base of the
NetShelter VX rear channel, and occupies the
bottom 2U of space behind the rear vertical
mounting rails.
See also
Follow the installation procedures in the manual included with your UPS.
Heavy
Use two people to install the UPS.
See also
Follow the procedures in the
instruction sheet included with your
Rack PDU Extender.