Installation Guide

9
4.
After the bedding material has been poured and beforeit sets, place the shower
base into the position with the drain assembly sliding over the PVC waste pipe. It
will be necessary to push the shower base until the top of the tile flange aligns with
the marks drawn on the studs and the front edge is contacting the rough floor
along the entire length of the shower base. Ensure tha
t the base is level in all
directions. You may need to use shims to hold the tray in the level until the bedding
settles and supports the tray. Remove all excessmortar.
See Fig. 7 for details.
5.
Allow the bedding material to completely harden before applying weight to the
bottom of the shower base.Install the cement board (or the wallboard) above the
tile flanges and secure it
to the studs.Put the tiles (or other finishing wall material)
over the cement board leaving 1/8" gap between the bottom of the tile and the
splash rim of the shower base.Use caulk to fill that gap.
See Fig. 8 and Fig. 9 for details.
Fig. 7
Fig. 8
Level base in two directions
8.1 8.2
8.3
8.4
Caulk
Waterproof Drywall to
the top of the tile ange
Stud
Drywall
Finished wall
overlaps the
dry wall adn
tile ange
1
8
"gap
Base