User's Manual
Table Of Contents
- 1. General
- 2. Introduction
- 3. Functional Description
- 4. Commissioning
- 4.1. General
- 4.2. High Power RU Mechanical Installation
- 4.3. Electrical Installation
- 4.3.1. Health and Safety for electrical installation
- 4.3.2. Property Damage Warnings for electrical installation
- 4.3.3. Connections
- 4.3.4. Grounding (Earthing)
- 4.3.5. Connection of the antenna cable
- 4.3.6. Mains power connection
- 4.3.7. Extension Unit port connection
- 4.3.8. External alarm In / Out port
- 4.3.9. RS 485 /+28 V port
- 4.3.10. Local interface port
- 4.3.11. Coupling Probe
- 4.3.12. Optical-fiber cable connection
- 4.3.13. Assembly instructions for optical LC patch cables
- 4.3.14. Optional equipment for optical fiber connection
- 4.4. Commissioning Flow-Chart
- 5. Alarms
- 6. Maintenance
- 7. Appendix
- 8. Index
4. Commissioning
Page 44 M0200A8C_uc_ION-U_H_7P_80-85P_17P_19P User’s Manual for ION
®
-U
Screw the adapter nut onto the body (2 N-m maximum torque).
figure 4-30 Tighten Opus short plug adapter nut
4.3.13.2. Connect Opus short plug to RU
Pull on the plug’s collar to remove the protection cap.
figure 4-31 Remove Opus short plug protective cap
Push the plug body into the receptacle until the collar is in the locked position.
The “UNLOCKED” label on the connector body will no longer be visible when
the connector is properly locked into the receptacle on the RU.
figure 4-32 Insert Opus short plug into RU receptacle
1
5
1
Protective cap
2
click
Unlocked label