4.1. High Power RU Mechanical Installation
4.1.1. General
Read the health and safety warnings in chapter 1.2.
1. Warning: Do not install the unit in a way or at a place where the
specifications outlined in the Environmental and Safety Specifications
leaflet of the supplier are not met.
2. WARNING: IMPROPER INSTALLATION CAN LEAD TO EQUIPMENT
FALLING CAUSING SERIOUS PERSONAL INJURY OR DAMAGE TO
EQUIPMENT. Installer must verify that the supporting surface will safely
support the combined load of the electronic equipment and all attached
hardware and components. The supporting wall should be solid wood or
concrete using appropriate screws and dowels (wall anchors).
3. Warning: It is recommended to use the mounting hardware delivered by the
manufacturer only. If different mounting hardware is used, the
specifications for stationary use of the Remote Unit must not be exceeded.
Note: Exceeding the specified load limits may cause the loss of warranty!
4. Warning: The unit is considerably heavy. Make sure that a suitable
mounting surface is used. Ensure there is adequate manpower to handle
the weight of the system.
5. Caution: Due to power dissipation, the Remote Unit may reach a very high
temperature. Ensure sufficient airflow for ventilation.
6. Note: When connecting and mounting the cables (RF, optical, mains, ...)
ensure that no water can penetrate into the unit through these cables.
7. Note: Observe all additional rules or restrictions regarding mounting that
apply to specific Remote Unit types.
8. Note: Observe all additional rules or restrictions regarding mounting that
apply to specific Remote Unit types. For details refer to the mechanical
specifications in the data sheet for the unit. Install the unit vertically with
the fan unit at the top. A maximum tilt angle of 25° from a vertical position
must be maintained, as shown in the following illustrations: