Commissioning the ION-M4/8 19"
Start
Mechanical installation
Prepare 19" rack for RU mounting with
guide rails. Weight of the RU is approx.
43 kg.
Manual for Remote
Unit
Electrical connections
Connect grounding cable and ground the
RU at connection terminals.
Mains
Switch mains power on. Switch mains
switches at PSU module at RU on.
Philips
screwdriver
RF connection
Connect antenna cable to antenna port.
Optical connections
Plug the optical fibre with E2000 APC8°
connector into the connector of the RU.
Mechanical installation
Mount RU to 19" rack, ensure suffient air
flow above and below the unit and avoid
thermal short circuits.
Preperation
Unpack RU and RU accessories.
External devices
Connect external devices to the external
in or alarm out connectors of the RU.
Guide rails
Screw
driver
Electrical connections
Connect AC (DC) power to the
connection terminals. Ensure there is a