Installation Guide

Table Of Contents
CommScope ERA
®
CAP L2 with Fiber Interface M0203A9B_uc
Page 26 © September 2022 CommScope, Inc.
Mount the Fiber CAP L2
1 Remove the four Phillips head screws from the left junction box cover of the kit and then remove the
junction box cover.
Figure 9. AC/DC Supply Junction Box Cover Screws
2 Insert a 16 AWG (1.31 mm
2
) 3-conductor AC input cable through the cable gland in the junction box.
3 Terminate the cables using WAGO 221 Series Lever-Nuts or equivalent connectors as shown in Figure 10.
Figure 10. AC/DC Supply Cable Terminations
4 Torque the cable gland nut to 3.0 Nm (26.5 in-lb) to secure the cable.
A plenum rated AC input cable is required when using the Plenum AC Power Supply kit or else the cable
must be routed to the junction box in conduit.
Cable Gland
ACN BLUE
ACL BROWN
GREEN/YELLOW
WAGO 221 SERIES LEVER-NUTS OR EQUIV.
(5 mm)
SEE CONNECTION DIAGRAM AT RIGHT.
AC INPUT CABLE
POWER
SUPPLY