3. Installing the Hardware
EAC-2100 Manual: (Draft, 02/01) Page 3-2
Figure 3-1. Hardware Installation Checklist
Checklist
q 1. EAC-2100 uncrated and contents checked. (Sec. 3.2.1)
q 2.
Holes drilled on the wall (for the wall bracket) or in the pad for the
pedestal mount (if using expandable anchors). (Sec 3.2.2)
q 3.
Hanging bracket or the pedestal positioned and bolted in place (orient the
pedestal for either front or rear RF cable entry, as required)
q 4. EAC-
2100 either hung on the wall bracket or placed on the pedestal, using
appropriate lifting aids. (Sec. 3.2.2)
q 5. With AC service breaker and the EAC-
2100 breaker off, ac electrical
connections made. (Sec. 3.3)
• Green or yellow/green to the safety ground
•
Brown to neutral (for 120VAC operation) or one side of 240 VAC
service
• Blue to 120VAC service or the other side of 240VAC service
• (Note: The power supplies in the EAC-2100 are auto-
ranging. The
brown and blue wires
may be connected to either 120 or 240 VAC
service.
q 5.
Antennas connected; signal level and isolation measured/adjusted. (Sec.
3.4)
q 6. External alarms/controls connected, if required. (Sec. 3.5)