Instruction manual
Installing Wall-Mount (MXD) Panels
62
Modero X® Series G4 Touch Panels Instruction Manual
1. Prepare the area by removing any screws or nails from the drywall before beginning the cutout process.
2. After ensuring proper placement, cut out the mounting surface for the Backbox, using the included Installation
Template as a guide.
3. Thread the incoming Ethernet and USB cables through the surface opening (FIG. 44 and FIG. 45). Note that these
figures show a landscape panel but the installation of a portrait panel is essentially the same, other than the vertical
orientation.
Leave enough slack in the wiring to accommodate any re-positioning of the panel.
FIG. 44 shows the MXD-1000 Backbox installation:
Making sure the actual cutout opening is slightly smaller than the provided
dimensions is highly recommended. This provides a margin for error if the opening
needs to be expanded. Too little wall material removed is always better than too
much.
FIG. 44 MXD-1000 Backbox Installation (Landscape)
#4 Screws
4X Knock-Outs
Remove for Cable
Routing as Needed
4X Installation Clamp
for Wall Thickness
.31 [12.0] to .98 [.25.0]