Manual

Before Installation
2 Amico Architectural
Note: Do not install studs unless
dimension ’A has been conrmed
by the Amico team
Rough Opening to accommodate
Amico Panel Wall Unit
IMPORTANT: READ AND UNDERSTAND ALL INSTRUCTIONS BEFORE COMMENCING WORK!
Prior to Start of Any On-Site Preparations
All site preparations must be completed prior to the delivery of the panel wall units. Please contact Amico to conrm and
review all information listed below. Failure to do so may result in discrepancies/misalignments during installation.
a. Wall Rough opening dimension, see Figure 1.
b. Stud gauge and size.
c. Wall thickness (e.g. including drywall and any additional paneling mounted on the nished wall).
d. Rough-in locations.
e. Blocking locations, if applicable.
f. Shipping restrictions.
NOTE: Ceiling grid must be installed after the middle section is installed and the rails are attached to the
units.
IMPORTANT: ALL ABOVE INFORMATION MUST BE COORDINATED, CONFIRMED AND APPROVED WITH
AMICO PRIOR TO ANY ON-SITE PREPARATION IN THE AREA WHERE THE HEADWALL WILL BE INSTALLED.
Figure 1 – Rough Opening
Building Studs
on site by others
Dimension ‘A’ to
be conrmed during
nal submittal