Owner's manual

www.amico.com 19
Initial Power-Up
Release the two latches on either side of the manifold control panel and remove the cover.
Verify the following:
Both master valves located on both header bars are turned fully counter clockwise (open).
All four line regulator isolation valves are open (handles horizontal).
Power supply has been connected.
Both Red empty indicators on the front of the manifold are illuminated.
If connected to a master alarm panel, “Secondary Supply alarm is activated.
Close 3/4” source shut-o valve.
“S-L-O-W-L-Y” open one cylinder on the right side of the manifold.
Verify the following:
Right bank Red “Empty LED goes out.
Right bank Green “in use LED illuminates.
Right bank cylinder contents gauge reads cylinder pressure.
“S-L-O-W-L-Y” open one cylinder on the left side of the manifold.
Verify the following:
Left bank Red “Empty LED goes out.
Left bank Yellow “Ready LED illuminates.
Left bank cylinder contents gauge reads cylinder pressure.
If connected to a master alarm panel, secondary supply alarm is not activated.
Close right bank cylinder. Slightly depress bleed valve located on the side of the regulator. Verify the
following:
Right bank cylinder contents gauge drops “S-L-O-W-L-Y”.
As the right cylinder contents gauge is nearly depleted, the manifold changes over to the left bank.
After change-over, the right bank Green “In Use LED goes out and the Red “Empty LED illuminates.
After change-over, the left bank Yellow “Ready LED goes out and the Green “In Use” LED illuminates.
Verify the line pressure gauge reading is acceptable.
“S-L-O-W-L-Y” open one cylinder on the right side of the manifold.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.