Installation Guide

11
710443-100 Rev. A 8/18
9
1a. 3 hole locations are predrilled into the Post [20] and can be used to mark drill locations in the Sliding Wall Post [21] from
the inside of shower. Remove Post and drill marked locations using a 1/8" (3.2mm) drill bit.
1b. Place Post [20] back onto Sliding Wall Post [21] and use 3 supplied M4x8 screws placing white plastic cups through each
screw which are used to hold Screw Cover Caps [26], then screw and secure Post into place onto the Sliding Wall Post.
1c. Cover each screw head with a Screw Cover Cap [26] to nish.
ATTACHING HARDWARE TO POST
10
Apply silicone at all inside and outside locations as shown.
Allow 24 hours for silicone to dry before use.
APPLYING SILICONE
3.2mm
Screw M4x8
1a
1b
1c
[25]
[26]
Allow 24 hours for silicone to dry before use.