Installation Guide
754964-100 Rev. A
6
7
5
Install temporary braces to hold
the center of the back and side
panels tight to the studs for
approximately 24 hours while
adhesive sets. Add cushioning
between panels and braces to
prevent scratching the panels.
When installing greenboard, position
drywall screws above the top nailing
flange. If you choose to screw
through the nailing flange, you
MUST drill clearance holes in the
flange to avoid cracking/damaging
the flange.
8
A) After greenboard is installed, apply finished sealant
bead to all edges and joints. Follow sealant
manufacturers’ recommended cure time.
B) Make connections to supply and drain lines.
GREEN BOARD